Sole BLU Ocean Living reached [XX]% structural progress in April 2026. The level 5 slab is complete. Façade work began this week. Here's how your future oceanfront condo on the Caribbean Sea in Puerto Morelos looks today.

Executive Summary — April 2026

  • Overall progress: [XX]% (vs [XX]% in March 2026)
  • Milestone of the month: Level 5 slab completed, main façade work underway
  • Next milestone (May 2026): Plumbing and sanitary installations on levels 3–5, finishes begin on floors 1–2
  • Units available in pre-sale: [X] (current price before the next increase)

What Moved Forward This Month

During April 2026, Eleva Capital's construction team completed the following work:

What this means for owners: if you own a unit on levels 1–3, you can now visit the site and stand where your living room will be. The proportions and the ocean view are exactly what you saw in the renderings. The Caribbean is right there — waiting for you.

  • Level 5 slab poured — floor structure 100% complete
  • Layout and installation of the façade begun on levels 1–3 of the east (ocean-facing) side
  • Installation of window systems (window frames and sliding doors) on levels 1 and 2
  • Electrical installations on levels 1–3 at 60%
  • Foundation pit for the rooftop pool completed

Upcoming Milestones — May and June 2026

So you can follow the progress with clear expectations:

May 2026

Plumbing and sanitary installations completed on levels 3–5. Roof waterproofing begins. First floor with finished flooring.

June 2026

Interior partition walls completed on floors 1–3. Wall base coat (mixteado) application begins. Level 4 windows installed.

July 2026 (projected)

First buyer walkthrough of the model units on levels 1–2.

A Message from the Team

"Every month we watch what began as a promise on paper turn into concrete, steel and ocean views. The Sole BLU team works knowing that every square meter we build represents someone's dream. That changes the way we show up to work."
— Construction Team, Eleva Capital Group

Haven't Reserved Your Unit Yet?

There are [X] units left in pre-sale. The current price expires when the next construction milestone closes. Once level 6 is complete, the price goes up. Now is the time to get in.

Profile of today's Sole BLU buyer: investors with experience in real estate or financial instruments looking to diversify with a tangible oceanfront asset. Mexican families who want their second home in the Riviera Maya. Foreigners who discovered Puerto Morelos and don't want to miss the pre-sale price.

An Eleva Capital Group advisor can show you the units available right now, the current pre-sale price and the payment plan during construction. Limited availability.

Book a Call — See Available Units Today